1

If the client fails to appoint a principal contractor when one is needed, who takes on those duties?

✓ The client

hard
2

Who prepares the health and safety file for a project with more than one contractor?

✓ The principal designer

hard
3

When is a construction project notifiable to HSE?

✓ If it lasts more than 30 working days with more than 20 workers at once, or exceeds 500 person days

hard
4

Who must notify HSE about a notifiable project, and where must the notice be displayed?

✓ The client, with the notice clearly displayed in the site office

hard
5

What is the most common enforcement action taken by HSE?

✓ Giving the dutyholder advice and writing to them to require action

hard
6

Who must the principal contractor liaise with throughout the principal designer's appointment?

✓ The principal designer

hard
7

When is a burn a specified injury under RIDDOR?

✓ When it covers more than 10% of the body, or significantly damages the eyes, lungs or other vital organs

hard
8

When is an injury from working in a confined space reportable as a specified injury?

✓ If it leads to hypothermia or heat illness, needs resuscitation, or means more than 24 hours in hospital

hard
9

A worker is off for 5 days after an accident. What does RIDDOR require?

✓ It must be recorded, but does not need to be reported

hard
10

How long must RIDDOR records be kept?

✓ At least 3 years

hard
11

For fatal and specified injuries, how quickly must the enforcing authority be notified?

✓ Without delay, by the quickest practicable means, then a report within 10 days

hard
12

An employee dies 6 months after a reportable accident, as a result of their injuries. What must the employer do?

✓ Notify the enforcing authority of the death without delay

hard
13

For RIDDOR scaffold collapse reports, how is the 5-metre height measured?

✓ From the base of the scaffold

hard
14

Which overhead line incident is a reportable dangerous occurrence under RIDDOR?

✓ Unintended contact by plant with an uninsulated line over 200 volts, or getting close enough to cause a discharge

hard
15

A wall of a building collapses unintentionally during demolition work. Is it reportable under RIDDOR?

✓ Yes — an unintended wall or floor collapse is reportable

hard
16

Can an appointed person cover for a first-aider who is away on planned annual leave?

✓ No — only unexpected absences

hard
17

Where portable chemical toilets are used, how many does HSE say are needed?

✓ One for every 7 people working a 40-hour week

hard
18

What must rest facilities include for pregnant women or nursing mothers, where necessary?

✓ Somewhere suitable to lie down

hard
19

What does a hazard pictogram showing a flame over a circle mean?

✓ Oxidising

hard
20

What does the exclamation mark hazard pictogram mean?

✓ Health hazard or hazardous to the ozone layer

hard
21

Why can some workers develop an allergy to cement, even after years of using it?

✓ Cement contains hexavalent chromium, which can sensitise the skin

hard
22

What type of vacuum cleaner does HSE say to use for asbestos dust?

✓ Type H

hard
23

How long does HSE say records of examinations, tests and repairs to COSHH control equipment should be kept?

✓ At least 5 years

hard
24

How should skin health surveillance for cement work be carried out?

✓ A trained responsible person checks new workers' skin early on, then at intervals

hard
25

What information about a load must employers give, where reasonably practicable?

✓ Its weight, and which side is heaviest if the weight is off-centre

hard
26

Does HSE still recommend using two workers to lay blocks heavier than 20 kg?

✓ No — it has not proved workable; lighter blocks are usually available instead

hard
27

What is the peak sound pressure exposure limit value?

✓ 140 dB(C)

hard
28

Why does HSE warn against giving workers hearing protection that blocks out too much noise?

✓ It can cause isolation, so people may not want to wear it

hard
29

Do you always have to measure noise with a meter to do a noise risk assessment on a construction site?

✓ No — it can be done without measuring, e.g. using manufacturers' data

hard
30

What are the daily exposure action and limit values for whole-body vibration?

✓ 0.5 and 1.15 m/s² A(8)

hard
31

How long using a hammer-action tool each day does HSE say is likely to put you above the vibration action value?

✓ More than about 15 minutes

hard
32

Since April 2022, which workers must employers provide PPE to, free of charge, where it is needed?

✓ Employees and "limb (b)" workers, such as many casual workers

hard
33

Why do some contractors ban rigger boots on their sites?

✓ People wearing them are more prone to ankle sprains

hard
34

Is PPE needed if a risk is already adequately controlled by other, equally or more effective means?

✓ No — the duty to provide PPE does not apply where the risk is adequately controlled by other equally or more effective means

hard
35

Apart from information and instruction, what does the law say the employer must organise, where appropriate, so workers know how to wear PPE?

✓ Demonstrations of how to wear it

hard
36

What rating of RCD gives useful protection against electric shock?

✓ No more than 30 mA

hard
37

How often should 230V equipment used on site have a visual check for damage?

✓ Every shift

hard
38

When is work on or near a live electrical conductor allowed?

✓ Only when it is unreasonable for it to be dead, reasonable to work live, and suitable precautions are taken

hard
39

Plant on site touches an overhead power line, but nobody is hurt. Is this reportable under RIDDOR?

✓ Yes — contact with overhead power lines by plant or equipment is reportable

hard
40

What does CDM 2015 say about fire-fighting equipment and alarm systems on site?

✓ They must be inspected, tested at suitable intervals and kept in good repair

hard
41

Regulation 29 of CDM 2015 requires steps to prevent injury from which risks?

✓ Fire or explosion, flooding, and asphyxiating substances

hard
42

When must work equipment whose safety depends on how it is installed be inspected?

✓ After installation and before first use, and after being assembled at a new site

hard
43

Equipment that needs inspecting is being sent to another site. What must go with it?

✓ Physical evidence that its last inspection was carried out

hard
44

Under PUWER, what should the information and instructions given to equipment users cover, where appropriate?

✓ How and when it may be used, foreseeable abnormal situations, and lessons from experience

hard
45

If an operator cannot see from the controls that nobody is in danger, what does PUWER say should happen before a machine starts?

✓ A suitable warning, such as an audible or visible signal, is given

hard
46

Under PUWER regulation 12, should protection against equipment hazards rely mainly on PPE and training?

✓ No — so far as reasonably practicable, measures should go beyond PPE, training and supervision

hard
47

What does CDM 2015 require where a pedestrian door or gate leads onto a traffic route?

✓ It must be sufficiently separated from the route

hard
48

If it is not reasonably practicable to keep vehicles and pedestrians apart, what does CDM 2015 require instead?

✓ Other means of protecting pedestrians, and effective warnings to anyone at risk of being crushed or trapped

hard
49

When planning work at height, what must an employer take account of?

✓ The risk assessment made under the Management of Health and Safety at Work Regulations

hard
50

A working platform used for construction must have been inspected in position before use if a person could fall how far from it?

✓ 2 metres or more

hard