Hardest CSCS Test Practice Questions
These are the hardest questions in our practice bank: exact numbers, legal duties and rules that are easy to mix up under test conditions. With a pass mark of 45 out of 50, these are the marks you can't afford to drop.
Difficulty is based on tagging in our question bank: hard questions need exact recall of a number, limit or duty; medium questions test concepts that are commonly confused. Master these first, then take a mock test to confirm your readiness.
If the client fails to appoint a principal contractor when one is needed, who takes on those duties?
✓ The client
Who prepares the health and safety file for a project with more than one contractor?
✓ The principal designer
When is a construction project notifiable to HSE?
✓ If it lasts more than 30 working days with more than 20 workers at once, or exceeds 500 person days
Who must notify HSE about a notifiable project, and where must the notice be displayed?
✓ The client, with the notice clearly displayed in the site office
What is the most common enforcement action taken by HSE?
✓ Giving the dutyholder advice and writing to them to require action
Who must the principal contractor liaise with throughout the principal designer's appointment?
✓ The principal designer
When is a burn a specified injury under RIDDOR?
✓ When it covers more than 10% of the body, or significantly damages the eyes, lungs or other vital organs
When is an injury from working in a confined space reportable as a specified injury?
✓ If it leads to hypothermia or heat illness, needs resuscitation, or means more than 24 hours in hospital
A worker is off for 5 days after an accident. What does RIDDOR require?
✓ It must be recorded, but does not need to be reported
How long must RIDDOR records be kept?
✓ At least 3 years
For fatal and specified injuries, how quickly must the enforcing authority be notified?
✓ Without delay, by the quickest practicable means, then a report within 10 days
An employee dies 6 months after a reportable accident, as a result of their injuries. What must the employer do?
✓ Notify the enforcing authority of the death without delay
For RIDDOR scaffold collapse reports, how is the 5-metre height measured?
✓ From the base of the scaffold
Which overhead line incident is a reportable dangerous occurrence under RIDDOR?
✓ Unintended contact by plant with an uninsulated line over 200 volts, or getting close enough to cause a discharge
A wall of a building collapses unintentionally during demolition work. Is it reportable under RIDDOR?
✓ Yes — an unintended wall or floor collapse is reportable
Can an appointed person cover for a first-aider who is away on planned annual leave?
✓ No — only unexpected absences
Where portable chemical toilets are used, how many does HSE say are needed?
✓ One for every 7 people working a 40-hour week
What must rest facilities include for pregnant women or nursing mothers, where necessary?
✓ Somewhere suitable to lie down
What does a hazard pictogram showing a flame over a circle mean?
✓ Oxidising
What does the exclamation mark hazard pictogram mean?
✓ Health hazard or hazardous to the ozone layer
Why can some workers develop an allergy to cement, even after years of using it?
✓ Cement contains hexavalent chromium, which can sensitise the skin
What type of vacuum cleaner does HSE say to use for asbestos dust?
✓ Type H
How long does HSE say records of examinations, tests and repairs to COSHH control equipment should be kept?
✓ At least 5 years
How should skin health surveillance for cement work be carried out?
✓ A trained responsible person checks new workers' skin early on, then at intervals
What information about a load must employers give, where reasonably practicable?
✓ Its weight, and which side is heaviest if the weight is off-centre
Does HSE still recommend using two workers to lay blocks heavier than 20 kg?
✓ No — it has not proved workable; lighter blocks are usually available instead
What is the peak sound pressure exposure limit value?
✓ 140 dB(C)
Why does HSE warn against giving workers hearing protection that blocks out too much noise?
✓ It can cause isolation, so people may not want to wear it
Do you always have to measure noise with a meter to do a noise risk assessment on a construction site?
✓ No — it can be done without measuring, e.g. using manufacturers' data
What are the daily exposure action and limit values for whole-body vibration?
✓ 0.5 and 1.15 m/s² A(8)
How long using a hammer-action tool each day does HSE say is likely to put you above the vibration action value?
✓ More than about 15 minutes
Since April 2022, which workers must employers provide PPE to, free of charge, where it is needed?
✓ Employees and "limb (b)" workers, such as many casual workers
Why do some contractors ban rigger boots on their sites?
✓ People wearing them are more prone to ankle sprains
Is PPE needed if a risk is already adequately controlled by other, equally or more effective means?
✓ No — the duty to provide PPE does not apply where the risk is adequately controlled by other equally or more effective means
Apart from information and instruction, what does the law say the employer must organise, where appropriate, so workers know how to wear PPE?
✓ Demonstrations of how to wear it
What rating of RCD gives useful protection against electric shock?
✓ No more than 30 mA
How often should 230V equipment used on site have a visual check for damage?
✓ Every shift
When is work on or near a live electrical conductor allowed?
✓ Only when it is unreasonable for it to be dead, reasonable to work live, and suitable precautions are taken
Plant on site touches an overhead power line, but nobody is hurt. Is this reportable under RIDDOR?
✓ Yes — contact with overhead power lines by plant or equipment is reportable
What does CDM 2015 say about fire-fighting equipment and alarm systems on site?
✓ They must be inspected, tested at suitable intervals and kept in good repair
Regulation 29 of CDM 2015 requires steps to prevent injury from which risks?
✓ Fire or explosion, flooding, and asphyxiating substances
When must work equipment whose safety depends on how it is installed be inspected?
✓ After installation and before first use, and after being assembled at a new site
Equipment that needs inspecting is being sent to another site. What must go with it?
✓ Physical evidence that its last inspection was carried out
Under PUWER, what should the information and instructions given to equipment users cover, where appropriate?
✓ How and when it may be used, foreseeable abnormal situations, and lessons from experience
If an operator cannot see from the controls that nobody is in danger, what does PUWER say should happen before a machine starts?
✓ A suitable warning, such as an audible or visible signal, is given
Under PUWER regulation 12, should protection against equipment hazards rely mainly on PPE and training?
✓ No — so far as reasonably practicable, measures should go beyond PPE, training and supervision
What does CDM 2015 require where a pedestrian door or gate leads onto a traffic route?
✓ It must be sufficiently separated from the route
If it is not reasonably practicable to keep vehicles and pedestrians apart, what does CDM 2015 require instead?
✓ Other means of protecting pedestrians, and effective warnings to anyone at risk of being crushed or trapped
When planning work at height, what must an employer take account of?
✓ The risk assessment made under the Management of Health and Safety at Work Regulations
A working platform used for construction must have been inspected in position before use if a person could fall how far from it?
✓ 2 metres or more