Legal Duties and Site Management
Who must the principal contractor liaise with throughout the principal designer's appointment?
AThe principal designer ✓
BThe local planning officer
CThe site's neighbours
DThe workers' bank
Answer & explanation
The correct answer is The principal designer.
Regulation 13(5) says the principal contractor must liaise with the principal designer for the duration of the principal designer's appointment and share relevant information.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM, principal contractor, principal designer. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
hardCDMprincipal contractorprincipal designer
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Which of these must the principal contractor organise during the construction phase?What is the principal contractor's main duty during the construction phase?What does CDM 2015 say about health and safety information or instructions that people must give?Under CDM 2015, who must you co-operate with on health and safety?