Legal Duties and Site Management
What is the principal contractor's main duty during the construction phase?
ATo design the permanent structure and choose its materials
BTo pay every worker on the site directly
CTo plan, manage and monitor it, and co-ordinate health and safety ✓
DTo notify the project to the local council
Answer & explanation
The correct answer is To plan, manage and monitor it, and co-ordinate health and safety.
Regulation 13 says the principal contractor must plan, manage and monitor the construction phase and co-ordinate matters relating to health and safety during it.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM, principal contractor. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumCDMprincipal contractor
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
What does CDM 2015 say about health and safety information or instructions that people must give?Which of these must the principal contractor organise during the construction phase?Under CDM 2015, who must you co-operate with on health and safety?Who must the principal contractor liaise with throughout the principal designer's appointment?