Which of these must the principal contractor organise during the construction phase?

AEach contractor's VAT returns and their accounts
BCo-operation between the contractors ✓
CThe client's planning application
DThe workers' holiday rota

Answer & explanation

The correct answer is Co-operation between the contractors.

Regulation 13(3) says the principal contractor must organise co-operation between contractors (including successive contractors on the same site) and co-ordinate their compliance with health and safety law.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM, principal contractor. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumCDMprincipal contractor