Working at Height
How often must a scaffold used for construction be inspected?
AOnce, when it is first put up, by the scaffolding contractor
BEvery 14 days, and after any alteration or adverse weather
CBefore it is first used, then at least every 7 days until it is finally taken down ✓
DOnce a month, or after any storm, by the site manager or a supervisor on duty
Answer & explanation
The correct answer is Before it is first used, then at least every 7 days until it is finally taken down.
A construction scaffold must be inspected before it is used for the first time and then every 7 days until it is removed — and also after anything that could have affected its safety.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Working at Height and covers scaffold, inspection, numbers. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyscaffoldinspectionnumbers
Test yourself on this topic
Earn XP and track your progress