Working at Height
Who should put up a mobile tower scaffold?
AA competent person, following the manufacturer's instructions ✓
BAnyone, as long as two people do it together
CThe person who will work on it, using their own judgement
DOnly the client's own maintenance staff, never outside contractors
Answer & explanation
The correct answer is A competent person, following the manufacturer's instructions.
Anyone erecting a tower scaffold should be competent to do so, and must refer to the manufacturer's instructions.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Working at Height and covers tower scaffold, competence. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easytower scaffoldcompetence
Test yourself on this topic
Earn XP and track your progress
More questions on this topic
How often does HSE say a safety harness should have a formally recorded detailed inspection?Where do you find the maximum safe height for a mobile tower scaffold?When should a safety harness have a pre-use check, and by whom?What does HSE say is the safest way to work on a fragile roof where possible?