Working at Height
A scaffold is part-built and not ready for use. What should be done?
ALet trades use the finished lifts while scaffolders work above
BPut up warning signs and physically block access to it ✓
CLeave it open, because people can see it is unfinished
DRemove the ladder, but leave the rest of the scaffold open
Answer & explanation
The correct answer is Put up warning signs and physically block access to it.
HSE says a scaffold that is not available for use should be marked with warning signs and physically blocked to stop access to the danger zone.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Working at Height and covers scaffold, signs. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.