Working at Height
How long must a copy of the scaffold plan be kept available?
AFor one week after it is built
BOnly until the very first weekly inspection
CIt does not need to be kept
DUntil the scaffold is dismantled ✓
Answer & explanation
The correct answer is Until the scaffold is dismantled.
HSE says a copy of the plan should be kept available to anyone involved until the scaffold is dismantled.