Skip to main content
Excavations and Confined Spaces

When should you decide what support an excavation will need?

ABefore you start digging ✓
BOnce the trench is about 1 metre deep
COnly if the sides start to crack
DAfter the first section has collapsed

Answer & explanation

The correct answer is Before you start digging.

HSE says before digging any trench, pit, tunnel or other excavation, decide what temporary support will be required. Battering the sides to a safer slope is another option.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Excavations and Confined Spaces and covers excavations, planning. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

easyexcavationsplanning

Test yourself on this topic

Earn XP and track your progress

Practice →

More questions on this topic