When should you decide what support an excavation will need?
ABefore you start digging ✓
BOnce the trench is about 1 metre deep
COnly if the sides start to crack
DAfter the first section has collapsed
Answer & explanation
The correct answer is Before you start digging.
HSE says before digging any trench, pit, tunnel or other excavation, decide what temporary support will be required. Battering the sides to a safer slope is another option.