Excavations and Confined Spaces

Apart from the start of each shift, when else must a supported excavation be inspected before work continues?

AOnly once a week, first thing on a Monday morning before the start
BOnly when a new worker joins the gang
COnly after the client has visited
DAfter anything that may affect its stability, or a fall of earth ✓

Answer & explanation

The correct answer is After anything that may affect its stability, or a fall of earth.

CDM 2015 requires inspection by a competent person at the start of each shift, after any event likely to affect the strength or stability of the excavation, and after any material unintentionally falls or is dislodged.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Excavations and Confined Spaces and covers excavations, inspection. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumexcavationsinspection

Test yourself on this topic

Earn XP and track your progress

Practice →

More questions on this topic