Excavations and Confined Spaces
Apart from the start of each shift, when else must a supported excavation be inspected before work continues?
AOnly once a week, first thing on a Monday morning before the start
BOnly when a new worker joins the gang
COnly after the client has visited
DAfter anything that may affect its stability, or a fall of earth ✓
Answer & explanation
The correct answer is After anything that may affect its stability, or a fall of earth.
CDM 2015 requires inspection by a competent person at the start of each shift, after any event likely to affect the strength or stability of the excavation, and after any material unintentionally falls or is dislodged.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Excavations and Confined Spaces and covers excavations, inspection. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumexcavationsinspection
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Which of these helps protect people in an excavation from falling material?A small trench is being dug next to a garden wall. What does HSE warn about?An excavation is being made safer by battering (sloping) its sides. What does HSE say about wet ground?Water is collecting in an excavation. What does HSE say should be done?