Skip to main content
Excavations and Confined Spaces

How much notice must be given to HSE before compressed air work starts?

AAt least 24 hours
BAt least 6 months
CNone
DAt least 14 days ✓

Answer & explanation

The correct answer is At least 14 days.

Regulation 6 says the contractor must give HSE written notice at least 14 days before the work starts, except in an emergency.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Excavations and Confined Spaces and covers compressed air, notification, numbers. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumcompressed airnotificationnumbers

Test yourself on this topic

Earn XP and track your progress

Practice →

More questions on this topic