How much notice must be given to HSE before compressed air work starts?
AAt least 24 hours
BAt least 6 months
CNone
DAt least 14 days ✓
Answer & explanation
The correct answer is At least 14 days.
Regulation 6 says the contractor must give HSE written notice at least 14 days before the work starts, except in an emergency.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Excavations and Confined Spaces and covers compressed air, notification, numbers. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumcompressed airnotificationnumbers
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Which regulations set the framework for tunnelling and other construction work in compressed air?Apart from HSE, who must be told about compressed air work?What is the maximum pressure anyone may be subjected to in compressed air work, except in an unforeseen emergency?When may workers be put through the procedure of decanting?