Safe Behaviour on Site

You turn up on a new site and are told to get straight to work without an induction. What should happen?

AYou can skip it if you have worked on similar sites before
BYou should have a site-specific induction before starting ✓
CYou only need an induction if you are new to construction
DAn induction is only needed on sites with more than 50 workers

Answer & explanation

The correct answer is You should have a site-specific induction before starting.

The principal contractor must ensure all workers have a site-specific induction, and any further information and training they need.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Safe Behaviour on Site and covers induction, scenario. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.