Accidents, Emergencies and First Aid
What must be in place on a construction site for dealing with foreseeable emergencies?
AA fire engine on standby whenever hot work is being carried out on site
BNothing, unless more than 50 people are working on the site at once
CSuitable arrangements, including plans for evacuating all or part of the site ✓
DA sign at the gate saying that the site is used at the visitor's own risk
Answer & explanation
The correct answer is Suitable arrangements, including plans for evacuating all or part of the site.
CDM 2015 requires suitable and sufficient arrangements for dealing with any foreseeable emergency, including procedures for evacuating the site or any part of it.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Accidents, Emergencies and First Aid and covers emergencies, CDM. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyemergenciesCDM