Skip to main content
Manual Handling

What does HSE say about two people carrying plasterboard sheets by hand?

AIt is a last resort ✓
BIt is always the best way, so it should be done every time
CIt is banned on all construction sites
DIt is only allowed for sheets over 3 metres long

Answer & explanation

The correct answer is It is a last resort.

HSE says the preferred order for plasterboard is to avoid, replace, then mechanise lifts. Two-person handling is a last resort, only when other options are exhausted, lifting is infrequent and other controls are in place.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Manual Handling and covers plasterboard, hierarchy. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumplasterboardhierarchy

Test yourself on this topic

Earn XP and track your progress

Practice →

More questions on this topic