Manual Handling
What does HSE say about two people carrying plasterboard sheets by hand?
AIt is a last resort ✓
BIt is always the best way, so it should be done every time
CIt is banned on all construction sites
DIt is only allowed for sheets over 3 metres long
Answer & explanation
The correct answer is It is a last resort.
HSE says the preferred order for plasterboard is to avoid, replace, then mechanise lifts. Two-person handling is a last resort, only when other options are exhausted, lifting is infrequent and other controls are in place.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Manual Handling and covers plasterboard, hierarchy. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumplasterboardhierarchy
Test yourself on this topic
Earn XP and track your progress
More questions on this topic
Do the Manual Handling Operations Regulations cover pushing and pulling?A designer is specifying kerbs for a road scheme. What does HSE suggest they consider first?How can planning deliveries reduce manual handling on site?Why does HSE say workers should be involved in solving manual handling problems?