1

How should traffic routes on a construction site be organised?

Answer: So that pedestrians and vehicles can move without risks to health or safety

2

What does HSE advise to reduce contact between pedestrians and vehicles?

Answer: Separate routes for pedestrians and vehicles where possible

3

What happens to pedestrians most often in workplace transport accidents?

Answer: They are hit or crushed by vehicles

4

What does CDM 2015 require where a pedestrian door or gate leads onto a traffic route?

Answer: It must be sufficiently separated from the route

5

You are walking across site and a marked pedestrian route goes the long way round. What should you do?

Answer: Use the marked pedestrian route

6

What is the best way to reduce the risks from reversing vehicles?

Answer: Remove the need to reverse, for example with one-way systems

7

If a vehicle has to reverse, what should happen to the reversing area?

Answer: It should be planned, clearly marked, and anyone who doesn't need to be there kept away

8

Which of these are visibility aids that can help a driver when reversing?

Answer: Fixed mirrors, cameras, and sensors that warn of or stop at an obstruction

9

A driver is reversing with a signaller (banksman) guiding them and loses sight of the signaller. What should the driver do?

Answer: Stop immediately

10

What does HSE say a signaller (banksman) guiding a reversing vehicle needs?

Answer: Training, a clear agreed signalling system, a safe position in view of the driver, and hi-vis

11

Where a driver might endanger someone by moving the vehicle, what does CDM 2015 require?

Answer: A warning must be given to anyone at risk, by the driver or the person directing them

12

Can you ride on a construction vehicle, for example on the side of a dumper?

Answer: Only in a safe place provided for that purpose

13

Loose material is being loaded into a lorry. Can someone stay on the lorry while it is loaded?

Answer: Only if a safe place of work is provided and maintained for them

14

What must be in place to stop vehicles falling into excavations or over the edge of earthworks?

Answer: Suitable measures, such as wheel stops at a safe distance from the edge

15

What causes most deaths involving site dumpers?

Answer: The driver being crushed when the dumper overturns

16

Why must a dumper driver wear the seat belt when the dumper has roll-over protection (ROPS)?

Answer: ROPS is not effective unless the driver is also wearing a suitable restraint

17

Which of these can cause a vehicle on site to overturn?

Answer: Travelling on steep slopes, soft ground, or too fast around corners

18

Who should be allowed to drive a site dumper?

Answer: Drivers who are trained, competent and authorised for that specific dumper

19

How should a dumper skip be loaded?

Answer: Evenly, not above the top edge of the skip, and not blocking the driver's view

20

What does CDM 2015 require to stop a parked vehicle rolling away?

Answer: Suitable steps to prevent or control unintended movement of any vehicle

21

Who should be supervised when driving on site, according to HSE?

Answer: All drivers, including visiting drivers

22

What four checks does HSE say a driver should make before leaving a vehicle?

Answer: Brakes on, engine off, key out, equipment safe

23

If a vehicle has to be parked on a slope, which way should it face?

Answer: Up or down the slope, never sideways across it

24

What should happen to the keys of site vehicles left overnight or over a weekend?

Answer: They should be kept secure

25

A trailer is being left parked on site. Is it enough to rely on the towing vehicle's brakes?

Answer: No — the trailer's brakes must be used too, as vehicle brakes are not designed to make trailers safe

26

What does CDM 2015 require at every loading bay?

Answer: At least one exit for the use of pedestrians only

27

A vehicle gate is not safe for people on foot to use. What does CDM 2015 require?

Answer: A clearly marked pedestrian door close by, kept free of obstructions

28

Under CDM 2015, what must happen to traffic routes on site once they are set up?

Answer: They must be signed where needed, regularly checked and properly maintained

29

When may a vehicle be driven along a traffic route on site?

Answer: Only if the route is free from obstruction and has enough clearance, so far as reasonably practicable

30

If it is not reasonably practicable to keep vehicles and pedestrians apart, what does CDM 2015 require instead?

Answer: Other means of protecting pedestrians, and effective warnings to anyone at risk of being crushed or trapped

31

What does HSE say parking areas should be like?

Answer: Level, firm, well lit and clearly marked, with safe walking areas

32

An excavator driver is stopping for a break. What should happen to the bucket?

Answer: It should be lowered to the ground

33

What does the code of practice "Safety at Street Works and Road Works" cover?

Answer: Signing, lighting and guarding of street works and road works

34

On which roads does the Safety at Street Works and Road Works code NOT apply?

Answer: Motorways and dual carriageways with a 50 mph or higher limit

35

What does following the street works code count as, legally?

Answer: Meeting the legal duty to sign, light and guard the works

36

The street works code gives standard layouts. When is a site-specific risk assessment needed?

Answer: For all works sites

37

Who may set up, maintain and remove signing, lighting and guarding at road works?

Answer: Only appropriately trained and competent people

38

Anyone placing portable traffic signals on a public road must have what?

Answer: A full understanding of the requirements and correct operation of the signals

39

For emergency road works, what does the code require?

Answer: Full signing, lighting and guarding as quickly as possible

40

If you must park your works vehicle in the road, which side should you get out?

Answer: The passenger side, away from the traffic

41

Which way should you face when setting out signs and cones on a live road?

Answer: Towards the oncoming traffic

42

While setting out signs and cones, what does the code say about phones?

Answer: You must not be distracted by phones, even hands-free ones

43

Which sign is set out first when setting up road works?

Answer: The "Road works ahead" sign

44

When taking down road works signs, which sign comes down last?

Answer: The "Road works ahead" sign

45

When setting out a lead-in taper of cones, where should you start?

Answer: At the kerb or road edge, working out towards the works

46

Visibility of the works is limited by a bend or the brow of a hill. What must you provide?

Answer: Extra advance signs, placed first

47

How should road works signs and cones be secured against wind and passing traffic?

Answer: With built-in weights, or sandbags placed low down

48

How high above the ground should the lower edge of a road works sign be, at least?

Answer: 300 mm

49

What should you do with a traffic cone whose reflective sleeve is damaged?

Answer: Do not use it

50

What is the safety zone at road works for?

Answer: Protecting you from traffic, and traffic from you

51

Can you store materials, equipment or vehicles in the safety zone?

Answer: No, they must not be placed in the safety zone

52

When must a safety zone be provided at road works?

Answer: When operatives are present, or a pedestrian walkway is in the carriageway

53

What must the working space be big enough for?

Answer: Plant to move and swing without entering the safety zone or footway

54

On roads with which speed limit must road works have warning lights lit in darkness or poor visibility?

Answer: 40 mph or more

55

When can flashing warning lights be used instead of steady ones?

Answer: Where street lighting is on and the limit is 40 mph or less

56

On a congested 30 mph road, a full lead-in taper is not possible. What does the code allow?

Answer: A shorter taper, but not less than 45 degrees in most cases

57

Where a reduced taper is used, how far before the taper must the first sign be, at least?

Answer: 20 metres

58

When a lane is closed for fixed works, what should be placed across the closed lane?

Answer: A traffic barrier with a red and white barrier sign

59

When remotely controlled Stop/Go boards are used, how far apart can the boards be, at most?

Answer: 200 metres

60

When can remotely controlled Stop/Go boards be used?

Answer: In daylight hours only

61

Using remote Stop/Go boards, how close must the operative be to both boards?

Answer: Less than 100 metres

62

Who is responsible for keeping pedestrians safe past footway works?

Answer: You, the people doing the works

63

What footway width does the code say to keep clear where possible, at least?

Answer: 1.5 metres

64

Which pedestrians does the code say to pay particular attention to around works?

Answer: Visually impaired people, wheelchair users and people with pushchairs

65

What must separate pedestrians from hazards at footway works?

Answer: A suitable barrier system

66

Who has a legal duty to co-ordinate all works in the streets they are responsible for?

Answer: The local highway authority

67

For planned works, who should visit the site in advance to decide the traffic management layout?

Answer: A competent person, who carries out a risk assessment

68

Where maintenance work has to be done on or near roads, what does HSE say about vehicle traffic?

Answer: Keep it away from the workers, using cones, barriers or closing the route