Under CDM 2015, what must happen to traffic routes on site once they are set up?

ANothing — once a traffic route is marked out it can be left alone for the whole job
BThey must be signed where needed, regularly checked and properly maintained ✓
CThey must be repainted every morning before work starts on site
DThey must be moved every week so drivers stay alert

Answer & explanation

The correct answer is They must be signed where needed, regularly checked and properly maintained.

Regulation 27 says each traffic route must be indicated by suitable signs where needed for health and safety, regularly checked and properly maintained.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Site Vehicles and Mobile Plant and covers traffic routes. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumtraffic routes