Site Vehicles and Mobile Plant
For planned works, who should visit the site in advance to decide the traffic management layout?
AThe first lorry driver to deliver materials to the site
BA competent person, who carries out a risk assessment ✓
CAny resident who lives on the street
DNobody, the layout is chosen on the day
Answer & explanation
The correct answer is A competent person, who carries out a risk assessment.
The code says for planned works a competent person should visit the site in advance and carry out a risk assessment to choose the right layout and equipment.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Site Vehicles and Mobile Plant and covers planning, risk assessment. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumplanningrisk assessment
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Who has a legal duty to co-ordinate all works in the streets they are responsible for?Where maintenance work has to be done on or near roads, what does HSE say about vehicle traffic?What must separate pedestrians from hazards at footway works?Which pedestrians does the code say to pay particular attention to around works?