Tools and Work Equipment

Under PUWER, a stop control must have priority over which other controls?

ANone — the start button always takes priority over any stop button fitted
BOnly the controls that are fitted on the back of the machine
COnly controls that are operated by a foot pedal
DAny control that starts the equipment or changes how it is operating ✓

Answer & explanation

The correct answer is Any control that starts the equipment or changes how it is operating.

Regulation 15 says the stop control must operate in priority to any control which starts or changes the operating conditions of the equipment.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Tools and Work Equipment and covers controls. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.