Legal Duties and Site Management
When must welfare facilities on site be provided?
AOnce the building has a roof on and all the outside walls are up
BOnly once more than 10 workers are on the site
CFrom the start of the construction phase, and maintained throughout ✓
DOnly during the winter months, from November to March
Answer & explanation
The correct answer is From the start of the construction phase, and maintained throughout.
HSE says the principal contractor must ensure suitable welfare facilities are provided from the start and maintained throughout the construction phase.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM, welfare. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyCDMwelfare
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Who must take steps to prevent unauthorised people getting onto a construction site?Under CDM 2015, what kind of construction work should you carry out?Which of these is a duty of the principal contractor?You notice something unsafe on site that could hurt someone else. What does CDM 2015 expect you to do?