Skip to main content
Working at Height

When does a scaffold need a bespoke design by calculation?

AWhen it is not built to a recognised standard configuration ✓
BOnly when the client asks for it in the contract
CNever, all scaffolds use the same basic design
DOnly when it is taller than 50 metres or goes over a road

Answer & explanation

The correct answer is When it is not built to a recognised standard configuration.

HSE says scaffolds built to a standard configuration, like NASC TG20 or the manufacturer's instructions, need no bespoke design. Others must be designed by calculation by a competent person.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Working at Height and covers scaffold, design. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumscaffolddesign

Test yourself on this topic

Earn XP and track your progress

Practice →

More questions on this topic