Unless the provider says otherwise, what loading should you assume a general-purpose scaffold can take?
A20 kN/m² (2,000 kg/m²)
B0.2 kN/m² (20 kg/m²)
C2 kN/m² (200 kg/m²) ✓
DAny load at all
Answer & explanation
The correct answer is 2 kN/m² (200 kg/m²).
HSE says assume a general-purpose duty rating of 2 kN/m² (200 kg/m²) unless the scaffold provider says otherwise.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Working at Height and covers scaffold, loading, numbers. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.