You plan to load out a scaffold platform with heavy materials. What should you do first?
AStack the materials at one end so the other end stays clear
BRemove a few ties so the scaffold can flex under the load
CSpread the load over two days so nobody notices the weight
DTell the scaffold provider, as a bespoke design will likely be needed ✓
Answer & explanation
The correct answer is Tell the scaffold provider, as a bespoke design will likely be needed.
HSE says scaffolds are not usually designed for heavy loads on platforms. Tell the provider before loading out, as a bespoke design will likely be needed.