Excavations and Confined Spaces
What information should a commercial client give contractors before excavation work begins?
AOnly the client's preferred start and finish times for the work
BOnly the colour of the finished surface
CGround conditions, underground features and services ✓
DNothing — finding out is entirely the contractor's job
Answer & explanation
The correct answer is Ground conditions, underground features and services.
HSE says commercial clients must give contractors information on ground conditions, underground structures or watercourses, and the location of existing services before work begins.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Excavations and Confined Spaces and covers excavations, client, planning. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumexcavationsclientplanning
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Where should a petrol-driven pump be placed when used to empty an excavation?What does HSE say should be considered at the design stage because it can remove the need for major excavations?Why does HSE warn about digging near trees?Under CDM 2015, what must be prevented where necessary at the edge of an excavation?