Legal Duties and Site Management
What must an exclusion zone around a demolition be big enough to do?
AFit every vehicle on site inside it at the same time
BGive workers somewhere to take their breaks
CHold all the skips needed for the whole job
DKeep all debris inside it if the structure collapses ✓
Answer & explanation
The correct answer is Keep all debris inside it if the structure collapses.
HSE says in a deliberate or accidental collapse, debris must remain within the exclusion zone.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers exclusion zone. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyexclusion zone
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
When deciding how to prevent collapse, what should a structural survey also consider?A scaffold is put up around a building being demolished. Does it let you make the exclusion zone smaller?Can a standard scaffold be used to hold up a building during demolition?Which method usually needs a smaller exclusion zone?