A job under a permit-to-work can’t be finished before the end of the shift. What should happen?

AThe permit can simply be left open overnight
BThe next shift should start again without a permit
CIt should be left in a safe state, with a proper handover ✓
DThe work should be rushed so that it is finished before the end of the shift

Answer & explanation

The correct answer is It should be left in a safe state, with a proper handover.

HSE says that if the job cannot be finished in one shift, you must make sure it will be left in a safe state, and the permit system should have a process for handing over.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers permit to work, handover. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumpermit to workhandover

Test yourself on this topic

Earn XP and track your progress

Practice →

More questions on this topic