Noise and Vibration
According to HSE, what is the best way to manage noise on a construction site?
AGet rid of the noisy process, or swap it for a quieter one ✓
BGive everyone the strongest ear defenders available
CLimit noisy work to the morning only
DPut up warning signs around all noisy machinery and plant on site
Answer & explanation
The correct answer is Get rid of the noisy process, or swap it for a quieter one.
HSE says eliminating noisy processes, or substituting a less noisy process, are the best ways of managing noise. Hearing protection comes last.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Noise and Vibration and covers noise, hierarchy. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumnoisehierarchy
Test yourself on this topic
Earn XP and track your progress
More questions on this topic
Is it acceptable to rely on hearing protection alone to control noise on site?Why does HSE warn against giving workers hearing protection that blocks out too much noise?What is a hearing protection zone?An excavator-mounted breaker is being used nearby. What does HSE suggest to protect other workers?