Noise and Vibration

How can a designer help remove noise from the building work itself?

ABy specifying harder bricks that need more cutting
BBy designing ducts into the structure, so channels don't have to be chased into walls ✓
CBy leaving all the decisions to the contractor on site
DBy making sure the site office is soundproofed

Answer & explanation

The correct answer is By designing ducts into the structure, so channels don't have to be chased into walls.

HSE says noise can be eliminated at the design stage, for example by designing ducts into a structure rather than chasing channels into walls.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Noise and Vibration and covers noise, design. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.