Electrical Safety
Refurbishment work could damage the building's existing electrics. What should happen first?
AWorkers should just take extra care when drilling near any sockets they can see
BThe relevant parts should be isolated, following safe isolation procedures ✓
CThe electrics can be left live, as long as an RCD is fitted to the circuits
DNothing — existing building wiring is the client's problem, not the contractor's
Answer & explanation
The correct answer is The relevant parts should be isolated, following safe isolation procedures.
Where work could disturb or damage the existing electrical system, the relevant parts should be isolated first, and safe isolation procedures must always be followed.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Electrical Safety and covers isolation, refurbishment. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumisolationrefurbishment
Test yourself on this topic
Earn XP and track your progress