Electrical Safety
How often does HSE suggest a combined inspection and test for 110V equipment on a construction site?
ABefore first use on site, then every 3 months ✓
BBefore first use on site, then every 2 years
COnly when the equipment is brand new from the hire shop
DEvery day, before each shift starts
Answer & explanation
The correct answer is Before first use on site, then every 3 months.
HSE suggests a combined inspection and test of 110V construction equipment before first use on site, then every 3 months. For 230V equipment it is monthly.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Electrical Safety and covers inspection, numbers, 110V. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
hardinspectionnumbers110V
Test yourself on this topic
Earn XP and track your progress
More questions on this topic
According to HSE, how often should a user check 230V mains equipment on a construction site?Which of these is a sign that a power tool cable is not safe to use?An RCD is fitted to the circuit you need to work on. What should you still do?You see burn marks and staining on a plug. What does this suggest?