What does Approved Document B say a proprietary sealing system around a pipe must do?
ALet smoke escape to the next room
BBe painted red so it is easy for inspectors to see
CKeep the fire resistance of the wall or floor ✓
DBe removed after the building is finished
Answer & explanation
The correct answer is Keep the fire resistance of the wall or floor.
Approved Document B says a proprietary, tested sealing system must maintain the fire resistance of the wall, floor or cavity barrier.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Fire Prevention and Control and covers fire stopping, penetrations. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumfire stoppingpenetrations