Fire Prevention and Control
You need to cut a new hole through a compartment wall for your cables. What should you do first?
ACut the hole and leave it open for the next trade
BGet permission, and make sure it will be properly fire-stopped afterwards ✓
CCut the hole as big as possible to save time later
DFill it with any expanding foam you can buy from a local DIY shop
Answer & explanation
The correct answer is Get permission, and make sure it will be properly fire-stopped afterwards.
A compartment wall is built to stop fire spreading. Approved Document B says every opening for services must be sealed with suitable fire-stopping, so the work must be planned and made good.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Fire Prevention and Control and covers fire stopping, penetrations. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumfire stoppingpenetrations
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
A fire door says "Automatic fire door keep clear". What does this tell you?What does the Building Safety Act 2022 call a building in England that is at least 18 metres high or has at least 7 storeys, with at least 2 homes?Which device can legally hold a self-closing fire door open?What height makes a block of flats in England a higher-risk building under the Building Safety Act 2022?