When must a risk assessment be reviewed?

AOnly once every five years, whether or not anything has changed on the site in the meantime
BOnly after an HSE inspector has visited the site and asked for it to be done
CIf there is reason to think it is no longer valid, or there has been a significant change ✓
DNever — once it is written it stays valid until the end of the project

Answer & explanation

The correct answer is If there is reason to think it is no longer valid, or there has been a significant change.

Regulation 3 says the assessment must be reviewed if there is reason to suspect it is no longer valid, or there has been a significant change in the matters it relates to.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers risk assessment. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumrisk assessment