Legal Duties and Site Management
Under CDM 2015, when must the client appoint a principal designer and a principal contractor?
AWhen there is, or is likely to be, more than one contractor on the project ✓
BOnly on projects that cost more than £1 million in total
COnly on projects that are going to last longer than six months in total
DOnly when HSE tells the client to make the appointments
Answer & explanation
The correct answer is When there is, or is likely to be, more than one contractor on the project.
Regulation 5 says where there is more than one contractor, or it is reasonably foreseeable that there will be, the client must appoint a principal designer and a principal contractor in writing.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM, duty holders. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumCDMduty holders
Test yourself on this topic
Earn XP and track your progress
Practice Tests