Before the construction phase starts, what must be drawn up?

AA final invoice for the client
BA construction phase plan ✓
CA list of all the workers' tools
DA design for the site office

Answer & explanation

The correct answer is A construction phase plan.

The client must ensure a construction phase plan is drawn up before the construction phase begins — by the contractor, or by the principal contractor where there is more than one contractor.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM, construction phase plan. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumCDMconstruction phase plan