When dismantling a lift, what stored energy must the plan take into account?

ASuspended masses in the counterweights, lift car and ropes ✓
BThe battery in the lift's emergency phone
CHeat from the lift car lighting
DNothing at all, because a switched-off lift has no stored energy left in it

Answer & explanation

The correct answer is Suspended masses in the counterweights, lift car and ropes.

HSE says planning must account for suspended masses and stored energy in the counterweights, lift cars, ropes and so on.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Lifting Operations and covers lift dismantling, stored energy. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumlift dismantlingstored energy