Skip to main content
Lifting Operations

If suspended lift parts must be released under load, what does HSE say is needed?

AA worker standing in the lift pit to guide it
BReleasing it slowly by hand from the car roof
CNothing extra if the building is empty
DA remote method with robust exclusion zones ✓

Answer & explanation

The correct answer is A remote method with robust exclusion zones.

HSE says release under load should only be used where it is the lowest-risk option, with a remote method and robust exclusion zones.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Lifting Operations and covers lift dismantling, exclusion zone. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

hardlift dismantlingexclusion zone

Test yourself on this topic

Earn XP and track your progress

Practice →

More questions on this topic