Lifting Operations

Who should plan the dismantling of a lift?

AAny demolition labourer who has been given a set of keys to the lift motor room
BCompetent people who understand that lift and how it is built into the structure ✓
CThe building's cleaning contractor
DWhoever is cheapest to hire for the job

Answer & explanation

The correct answer is Competent people who understand that lift and how it is built into the structure.

HSE says lift dismantling must be planned by competent people who understand the specific lift and how it is built into the structure. Consider specialist contractors.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Lifting Operations and covers lift dismantling, competence. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.