Who should plan the dismantling of a lift?
AAny demolition labourer who has been given a set of keys to the lift motor room
BCompetent people who understand that lift and how it is built into the structure ✓
CThe building's cleaning contractor
DWhoever is cheapest to hire for the job
Answer & explanation
The correct answer is Competent people who understand that lift and how it is built into the structure.
HSE says lift dismantling must be planned by competent people who understand the specific lift and how it is built into the structure. Consider specialist contractors.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Lifting Operations and covers lift dismantling, competence. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easylift dismantlingcompetence
Test yourself on this topic
Earn XP and track your progress
More questions on this topic
Which areas should exclusion zones cover when lift parts are released?What does the standard quoted by HSE say about lift equipment during dismantling?If suspended lift parts must be released under load, what does HSE say is needed?What does HSE say accident investigations found about lift dismantling and demolition?