Legal Duties and Site Management
How much notice does HSE say to give the local authority before starting demolition?
AAt least 48 hours
BAt least 6 weeks ✓
CAt least 6 months
DNone is needed
Answer & explanation
The correct answer is At least 6 weeks.
HSE says give the local authority (building control) notice at least 6 weeks before you intend to start demolition.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers planning, notice, numbers. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumplanningnoticenumbers