Who must write the demolition method?
AThe newest labourer on site
BA competent person ✓
CThe building's owner
DThe local newspaper
Answer & explanation
The correct answer is A competent person.
HSE says the demolition method must be written by a competent person, cover all the hazards of the structure and site, and be shared with the team.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers planning, method statement. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyplanningmethod statement
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
How much notice does HSE say to give the local authority before starting demolition?Which regulations apply to demolition work, as they do to other construction work?If danger cannot be fully prevented during demolition, what does CDM regulation 20 require?Who plans and manages health and safety during the demolition work itself?