Legal Duties and Site Management

Who plans and manages health and safety during the demolition work itself?

AThe principal contractor ✓
BThe building's insurer
CThe local fire and rescue service
DThe nearest neighbour

Answer & explanation

The correct answer is The principal contractor.

HSE says the principal designer manages health and safety before demolition starts, and the principal contractor does so during demolition.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM, duty holders. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.