What information about the structure must the client give the demolition contractor before work starts?
AOnly the address of the building and the date work should finish
BThe names of everyone who has ever lived in the building
CThe price the client paid for the building originally
DAsbestos, structural stability, past alterations and below-ground services ✓
Answer & explanation
The correct answer is Asbestos, structural stability, past alterations and below-ground services.
HSE says contractors must be given information about the structure, including asbestos, structural stability, past alterations and below-ground services.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers pre-construction information. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumpre-construction information
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
When should live services below ground in the work area be identified?Before awarding a complex demolition contract near roads or in a town, whose advice does HSE recommend?Who plans and manages health and safety during the demolition work itself?What sequence of work does HSE say demolition should follow?