What sequence of work does HSE say demolition should follow?

AWhatever order is quickest and cheapest for the machine operator
BOne that removes any chance of an uncontrolled collapse ✓
CAlways starting with the main load-bearing walls
DAlways starting at ground level and working upwards

Answer & explanation

The correct answer is One that removes any chance of an uncontrolled collapse.

HSE says adopt a sequence of work that eliminates the possibility of an uncontrolled collapse.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers stability, sequence. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.