Which parts of a structure does HSE say to remove first?
AElements that are not critical to its stability ✓
BThe main columns that hold up the roof
CThe foundations under all of the external walls
DThe ground floor slab under the building
Answer & explanation
The correct answer is Elements that are not critical to its stability.
HSE says remove elements that are not critical to stability first, as part of a sequence that prevents uncontrolled collapse.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers stability, sequence. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumstabilitysequence
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
What sequence of work does HSE say demolition should follow?Why might a partly demolished floor need temporary support?Before awarding a complex demolition contract near roads or in a town, whose advice does HSE recommend?Who should decide whether temporary support is needed during alteration or demolition?