Should an exclusion zone stay the same size for the whole demolition project?

AYes, it must never change once it has been set out on day one
BYes, unless the client asks for a change
CNo, it is only needed on the last day
DNo, it may need to change as the work progresses ✓

Answer & explanation

The correct answer is No, it may need to change as the work progresses.

HSE says exclusion zones may need to change as the project progresses, so the plan should allow for this.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers exclusion zone, planning. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.