Legal Duties and Site Management
Should an exclusion zone stay the same size for the whole demolition project?
AYes, it must never change once it has been set out on day one
BYes, unless the client asks for a change
CNo, it is only needed on the last day
DNo, it may need to change as the work progresses ✓
Answer & explanation
The correct answer is No, it may need to change as the work progresses.
HSE says exclusion zones may need to change as the project progresses, so the plan should allow for this.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers exclusion zone, planning. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumexclusion zoneplanning
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Which method usually needs a smaller exclusion zone?If a collapse could throw debris outside the site onto a road, what might reduce the risk?A scaffold is put up around a building being demolished. Does it let you make the exclusion zone smaller?If there is not enough space around a structure for the exclusion zone a method needs, what does HSE suggest?