Skip to main content
Legal Duties and Site Management

If a collapse could throw debris outside the site onto a road, what might reduce the risk?

AA road closure, agreed with the highway authority ✓
BAsking drivers to slow down as they pass the site
CWorking only at night when it is dark
DPutting up a sign that says "Demolition in progress"

Answer & explanation

The correct answer is A road closure, agreed with the highway authority.

HSE says a road closure may reduce the risk. Discuss it with the local highway authority before tendering.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers exclusion zone, public. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

mediumexclusion zonepublic

Test yourself on this topic

Earn XP and track your progress

Practice →

More questions on this topic