Legal Duties and Site Management
If a collapse could throw debris outside the site onto a road, what might reduce the risk?
AA road closure, agreed with the highway authority ✓
BAsking drivers to slow down as they pass the site
CWorking only at night when it is dark
DPutting up a sign that says "Demolition in progress"
Answer & explanation
The correct answer is A road closure, agreed with the highway authority.
HSE says a road closure may reduce the risk. Discuss it with the local highway authority before tendering.