Who should design bracing and propping during demolition?
AThe demolition machine operator on the day
BWhoever is nearest the props
CThe site security guard
DExperienced temporary works designers ✓
Answer & explanation
The correct answer is Experienced temporary works designers.
HSE says all bracing and propping should be designed by experienced temporary works designers.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers temporary works, competence. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
mediumtemporary workscompetence
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
If there is not enough space around a structure for the exclusion zone a method needs, what does HSE suggest?How does HSE suggest removing the need for workers to be at height during demolition?If a collapse could throw debris outside the site onto a road, what might reduce the risk?Should an exclusion zone stay the same size for the whole demolition project?