Legal Duties and Site Management
A new starter did an induction on another of your firm’s sites last month. What does HSE say they need here?
AA suitable induction that is specific to this site ✓
BNothing more, because one induction covers every site
COnly a copy of the company health and safety policy
DA new CSCS card for this site
Answer & explanation
The correct answer is A suitable induction that is specific to this site.
HSE says contractors must make sure all workers under their control have a suitable, site-specific induction, unless the principal contractor has already provided one.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, induction. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyCDM 2015induction
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
Under CDM 2015, what must a contractor ensure about welfare facilities for their own workers?Before a worker uses a mobile elevating work platform, what should their contractor check?Before starting construction work, a contractor must be satisfied of what about the client?Who must plan, manage, monitor and coordinate health and safety for the whole construction phase?