A new starter did an induction on another of your firm’s sites last month. What does HSE say they need here?

AA suitable induction that is specific to this site ✓
BNothing more, because one induction covers every site
COnly a copy of the company health and safety policy
DA new CSCS card for this site

Answer & explanation

The correct answer is A suitable induction that is specific to this site.

HSE says contractors must make sure all workers under their control have a suitable, site-specific induction, unless the principal contractor has already provided one.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, induction. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.