Legal Duties and Site Management
Before starting construction work, a contractor must be satisfied of what about the client?
AThat the client has paid a deposit
BThat the client is aware of their duties under CDM 2015 ✓
CThat the client has visited the site
DThat the client holds a CSCS card
Answer & explanation
The correct answer is That the client is aware of their duties under CDM 2015.
Regulation 15(1): a contractor must not carry out construction work on a project unless satisfied that the client is aware of the client’s duties under the Regulations.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, client. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
hardCDM 2015client
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
On a job with only one contractor, who must make sure a construction phase plan is drawn up?Under CDM 2015, what must a contractor ensure about welfare facilities for their own workers?On a project with more than one contractor, whose directions must each contractor comply with?A new starter did an induction on another of your firm’s sites last month. What does HSE say they need here?