Legal Duties and Site Management

Before starting construction work, a contractor must be satisfied of what about the client?

AThat the client has paid a deposit
BThat the client is aware of their duties under CDM 2015 ✓
CThat the client has visited the site
DThat the client holds a CSCS card

Answer & explanation

The correct answer is That the client is aware of their duties under CDM 2015.

Regulation 15(1): a contractor must not carry out construction work on a project unless satisfied that the client is aware of the client’s duties under the Regulations.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, client. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.

hardCDM 2015client