Legal Duties and Site Management

On a job with only one contractor, who must make sure a construction phase plan is drawn up?

ANobody, because plans are only needed with two or more contractors
BThe contractor ✓
CThe local authority
DHSE

Answer & explanation

The correct answer is The contractor.

Regulation 15(5): where there is only one contractor, the contractor must draw up a construction phase plan, or make arrangements for one, as soon as practicable before setting up the site.

This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, construction phase plan. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.