Legal Duties and Site Management
Before a contractor starts work on a site, what must have happened about site access?
AReasonable steps must have been taken to stop unauthorised people getting in ✓
BThe local council must have inspected and approved the position of every gate and fence
CEvery visitor must have been given a CSCS card
DThe police must have been told the site is opening
Answer & explanation
The correct answer is Reasonable steps must have been taken to stop unauthorised people getting in.
Regulation 15(10): a contractor must not begin work on a construction site unless reasonable steps have been taken to prevent access by unauthorised persons.
This is one of 961 free CSCS test practice questions on Pass the Site Test. It is from the topic Legal Duties and Site Management and covers CDM 2015, site security. Every question is our own, written from UK health and safety law and HSE guidance. Browse all questions or take a free mock test.
easyCDM 2015site security
Test yourself on this topic
Earn XP and track your progress
Practice Tests
More questions on this topic
What must a contractor do with the construction work they and their workers carry out?On a project with more than one contractor, whose directions must each contractor comply with?A contractor wants to take someone on for a task. What does CDM 2015 say about that person?On a job with only one contractor, who must make sure a construction phase plan is drawn up?